PIANC Panama - Agenda

08:30 - 10:00
Room: Track B (Panama 3 - 4th Floor) - Wide Screen (16:9) Format
Chair/s:
Craig Philip
THE FIRST PHASE OF EXPANSION OF THE KINGSTON CONTAINER TERMINAL
Eric FERNAGU 1, Cédric GARNIER 2, Philippe DELHOMME 3
1 Egis Ports
2 CMA Terminals Holding
3 CMA Ships

Kingston Freeport Terminal Limited (KFTL) owned by CMA CGM got awarded in April 2015 the 30 years concession for the Kingston Container Terminal (KCT). This Container terminal, with current capacity of 2.8 MTEU, is conveniently situated on a direct line between the U.S. and the Panama Canal, and between Europe and the Panama Canal, would ensure a leadership position for the Port as a regional transhipment hub.

The concession contemplates improvement works that will be implemented in a two-phased development:

  • Phase 1 aims at accommodating the existing terminal (Quays and nautical access) to the Neopanamax container vessels, through deepening and realignment of the nautical accesses and refurbishment of 1 200 lm of existing quays. This will allow access as from end 2017 of Neopanamax vessels with 14.7 m draft ;
  • Phase 2 will consist of the deepening of the nautical accesses to allow access to 15.5m draft vessels and of the expansion of the terminal capacity to 3.6 million TEU.

The presentation is proposed to focus on the first phase being implemented currently and more particularly the following challenges of the project:

The conception of the nautical accesses:

It consists in realignment and deepening for Neopanamax 14,000 TEU vessels, considering the technical and environmental constraints of the site:

  • The 15km long channel passes through very sensitive environmental areas including but not limited to the Palisadoes-Port Royal Protected Area with reefs, heritage historical sites such as the Port Royal Sunken City and sea grass.
  • The so-called inner channel is bended passing through very shallow areas with sustained regular transversal wind. The optimization of the realignment and deepening has been performed on basis of vertical detailed design approach as well as horizontal detailed design approach in the CMA CGM Fleet Center Full Bridge Simulator.

The planning of the works:

In order to ensure continuous operations of the Terminal, as well as its increase of throughput during the works started in 2016 and due to be completed by end 2018, the sequencing of the works has been established on basis of detailed modelling of the capacity of the terminal, during the expansion phase. The selected scenario was consisting in phasing in 3 upgrade stages as follows: 600m / 300m / 300m. The overall project, including quay upgrade, yard pavement rehabilitation and new gantry cranes delivery has been optimized in light of this best operational scenario.

The design of the quay wall upgrade:

As from the start of the Project, CMA-CGM has always looked at taking benefits of the existing structures (2 400 lm of berth with allowed draft of 13m) instead of building extension to the existing berths. This has required an innovative and state-of-the-art approach in order to ensure the feasibility of the project to go over the following obstacles:

  • The seismic context with 475 year return period event seismic acceleration reaching 0.29g coupled with a complex geotechnical context (more than 12m thick liquefiable soils on top of stiff to hard clays without presence of substratum). The adopted approach -to confirm and optimize the seismic design criteria- has coupled seismotectonic analysis, PSHA to define site-specific response spectra and specific geotechnical investigation (cross-holes).

The nature of the existing quay structure, being a combi-wall structure designed for 13m draft vessels. Innovative solutions have been investigated and finally adopted to mitigate the increase of the dredged depth and by consequence of the associated reduction of the embedded length of piles and steel sheet and to cope with the loss of mobilized passive pressure in front of the quay no longer sufficient to resist to the active pressure due to earth and loading. The finally adopted structure will be presented.


Reference:
Tu-S4-B - Ports-2
Session:
Session 4 - Maritime Port planning and operations
Presenter/s:
Eric FERNAGU
Room:
Track B (Panama 3 - 4th Floor) - Wide Screen (16:9) Format
Chair/s:
Craig Philip
Date:
Tuesday, 8 May
Time:
08:30 - 10:00
Session times:
08:30 - 10:00